0728608043 info@crone-tech.co.ke 24096-00100. Dar-eslam Rd, Kamkis Plaza

Design, Installation and Commissioning of UPS Power system for Kenya Airports Authority

0 Comments

The project involved Design, Installation and commissioning of 500 KVA standby UPS system for Jommo Kenyatta International Airport.

Client: Kenya Airports Authority(Subcontract)

Status: Completed

Scope

· Design Of AVS/UPS parallel Power system

· Design of Raw power supply system to UPS(Cable sizing and Protection)

· Design of Power distribution system from UPS Switch room to Terminals within airport

· Installation Of all cabling for power supply to UPS and clean power to Terminals,1,2,3 and International Arrivals

· Commissioning, Testing and Handover of system

Leave a Reply